Mortar bags Calculator

Convert a known mortar volume into bags.

Back to the toolbox
01

Your measurements

Choose the unit beside each measurement. Changing a unit converts your value.

m³
L
%

View your estimate

Example values are a starting point. Check product yields and specifications before ordering.

YOUR ESTIMATE

Bags to buy

17
Volume including waste0.22 m³
Yield per bag13 L
Purchased yield0.221 m³

Same quantity, different units

Volume including waste

m³
0.22
yd³
0.2877
ft³
7.7692

Whole quantities are rounded up.

How it's calculated

Bags = round up [volume × (1 + waste ÷ 100) ÷ mixed yield per bag].

Calculations use consistent units for your selected measurements. The waste allowance is applied once to the measured requirement. Whole purchase quantities are rounded up.

What this estimate includes

This tool requires your mortar volume estimate. Product yield varies with mix and water content.

QUIKRETE product yields

Quantity and arithmetic estimates only. Use project specifications for installation and design requirements.

Mortar bags Calculator guide

Use the method below to check your estimate before turning it into an order.

Use mixed yield per bag

Divide required finished volume including allowance by the yield on your product, then round up to whole bags. Dry bag weight is not mixed volume.

Bags = round up [volume × (1 + waste ÷ 100) ÷ mixed yield per bag].

Worked examples in metric and imperial units

These examples describe the same project using the calculator’s starting values. Converted inputs are rounded here for readability; calculations use full precision. These reference examples stay fixed when you edit the calculator above.

Metric worked example

Required wet mortar volume
0.2 m³
Mixed mortar yield per bag
13 L
Waste allowance
10 %

Bags to buy: 17

The purchase count is rounded up to a whole unit.

Imperial worked example

Required wet mortar volume
0.2616 yd³
Mixed mortar yield per bag
0.4591 ft³
Waste allowance
10 %

Bags to buy: 17

The purchase count is rounded up to a whole unit.

Units and products around the world

Choose the system matching your measurements. Product sizes, pack yields and installation specifications vary by supplier and country; replace example inputs with your actual project values.

1 m³ = 1,000 L ≈ 1.30795 yd³. One cubic yard is 27 ft³. Convert dimensions before multiplying; millimetres and inches cannot be multiplied directly with metres and feet.

Frequently asked questions

Can I infer yield from bag weight?

No. Equal-weight products can have different yields. Use the product data sheet and prescribed mixing instructions.

What should I check before using this estimate?

This tool requires your mortar volume estimate. Product yield varies with mix and water content.

Should I use the example allowance?

Choose an allowance for your measured project, layout and product. The starting percentage is an editable example. Do not apply it again if the input already includes the same allowance.